Wednesday, June 4, 2008

Major Project



ABOVE: 1:10 Detail Model of Timber Portal Frame, Corner with End Wall. NOTE: Footings not shown in model as model wouldn't stand up independently with them attached, please refer to poster for footing detail.

ABOVE: Photo of Poster.

Major Project-Architect


ABOVE: Ashton Raggatt McDougall, Docklands Port 1010, Digital Harbour

The building that I chose to use as my influence for the design of my warehouse was Ashton Raggatt McDougall's Docklands Port 1010 building, which is part of the digital harbour development. The focus of Docklands Port 1010 was to create new office spaces specifically designed for the use by the IT industry. Tinted glass has been used to provide shade to the offices inside, which is a technique that I will also be using for my offices. I have also decided to explore the pattern used on the facade of this building, but using timber battens instead to make up the shapes.

Monday, June 2, 2008

Deakin Waterfront Extension (Dennys Lascelles Building)-Site Visit (28/04/08)


ABOVE: Extension to existing buidling using pre-cast concrete construction.


ABOVE: This photo shows the connection from pre-cast concrete lift shaft to steel UB column using steel connection.

ABOVE: This photo shows a concrete column supported by temporary bracing.



ABOVE: This photo shows fire protected columns and columns that don't need fire protection as they will be removed.



ABOVE: This photo shows steel wall framing.


ABOVE: This photo shows timber wall framing.

ABOVE: This photo shows a steel portal frame that makes up the extension on top of the existing building.

ABOVE: This photo shows a suspended ceiling.

TAC Building-Site Visit (12/05/08)


ABOVE: Exerior overall photo of TAC building.


ABOVE: Photo of pre-cast concrete panels supported by temporary bracing.


ABOVE: Bondek, which is a product used as formwork for the pouring of concrete slabs. Bondek is not removed, becoming non-structural once the concrete dries. The Bondek can hae holes penetrated in it for the provision of services.

Bendigo Market Place Extension Construction Site-Visit 3(18/0508)


ABOVE: Hollow concrete slab on pre-cast concrete panels, supported by temporary bracing (in background).


ABOVE: Roof insulation and cladding has been installed in some parts of building.

ABOVE: Trench mesh ready for concrete slab installation. Air conditioning vents have been installed in the areas where the roof cladding and installation have also been installed.
Alot has happened since my last visit to the site. The roof cladding and insulation have been installed on some of the building, along with air conditioning vents. Trench mesh has been laid down ready for the installation of a poured concrete slab.
Alot has happened

Bendigo Market Place Extension Construction Site-Visit 2 (26/04/08)




ABOVE: Photo of pre-cast concrete load-bearing panels with temporary bracing supporting them. A pre-cast concrete lift shaft has also been constructed.


ABOVE: Photo of steel portal frame supported by load-bearing pre-cast concrete panels. Pre-cast concrete lift shaft is located to the far left of the photo.


ABOVE: Steel 'parallel chord' truss, load-bearing pre-cast concrete panels in background and pre-cast concrete lift shaft with temporary supports.
Alot has happened since my last visit to the site a month ago. A pre-cast concrete lift shaft has been constructed, more concrete walls have been installed and hollow core concrete slabs have begun to be used.